The Miller Avenue Streetscape Project is designed to make Miller Avenue safer, more efficient and enjoyable for all who use this busy roadway, including pedestrians, bicyclists, motorists, transit users, visitors and more. The main components of the project include:

A continuous bike lane from Sunnyside to Almonte

Sidewalk repair and widening in some sections

Improvements to bus shelters

Improvements to the drainage and pavement of the roadway

The project is managed by the City of Mill Valley and was completed in November 2017.

For more details, visit the City of Mill Valley website

Allocated Funding For Miller Avenue

Date Funding allocated
June 2016 $3.25 million to complete construction
March 2016 $4.8 million in Measure A funds and $1,211,798 in State Local Partnership Program (SLPP) funds for construction
May 2015 $1.4 million to complete the final design
March 2010 $550,000 to develop the Miller Avenue Streetscape Plan and environmental review
November 2006 $250,000 for conceptual engineering and environmental phases
Total: $18.3 million